Pricing methodology

How to price a commercial renovation

Build a defensible budget: itemised vs lump-sum, prelims breakdown, contingency 10–20%, scope-change risk and payment milestones. Sourced 2026 SG ranges throughout.

Two ways to price a commercial renovation

Almost every Singapore commercial fit-out is priced one of two ways: lump-sum (fixed price against a defined scope) or itemised (priced bill-of-quantities you can negotiate line-by-line). Lump-sum is faster and lower-stress; itemised is cheaper and more transparent. For projects above S$300k, itemised almost always wins on total cost.

Either way, your final number is construction + prelims + professional fees + permits + contingency. Skip any of these and you’ll be paying it later out of pocket.

Pricing methods

Per sqft

Per square foot

Most common for office and retail with a defined finish spec.

  • Best for: Standard fit-outs
  • Range: S$50–300/sqft
  • Accuracy: ±15–20%
Lump sum

Fixed lump-sum

Detailed scope locked into a single price.

  • Best for: Complex projects
  • Quote time: 2–3 weeks
  • Accuracy: ±5–10%
Cost plus

Cost-plus

Materials at cost + contractor management fee.

  • Best for: High-end projects
  • Margin: 15–25%
  • Transparency: Full visibility

Sourced 2026 bands by space type

Use these as your top-line price anchor before scoping in detail.

Office — standard fit-out
S$100–180/sqft Source: JLL Asia Fit-Out Cost Guide

Full fit-out with meeting rooms, M&E, finishes. Tier-A office.

Office — premium CBD
S$180–280/sqft Source: CBRE Asia Pacific Fit-Out Cost Guide

CBD A-grade — bespoke carpentry, integrated AV, premium finishes.

Retail — mall unit
S$150–280/sqft Source: Moom 2024 SG Office Fit-out Cost Benchmarks

Mid-tier mall (Jurong Point, NEX, JEM).

F&B — restaurant
S$200–400/sqft Source: Moom 2024 SG Office Fit-out Cost Benchmarks

Mid-tier restaurant — proper exhaust, grease trap, decent FOH.

Clinic — GP / dental
S$150–350/sqft Source: MOH Healthcare Services Act licensing

MOH HCSA-ready partitions, infection-control finishes, sterilisation room.

Industrial — light
S$80–150/sqft Source: BCA Public Sector Construction Demand Forecast

Light industrial fit-out — office mezzanine, production zones.

Typical budget breakdown

For a S$300k commercial fit-out, here’s where the money typically goes. Adjust contingency upward (15–20%) for older buildings, change-of-use projects, or anything involving structural alterations.

Category % of total On S$300k
Construction (labour + materials)60–70%S$180–210k
Prelims (site setup, supervision, hoarding)8–12%S$24–36k
Professional fees (ID, QP, M&E)10–15%S$30–45k
Permits & submissions2–5%S$6–15k
Contingency10–20%S$30–60k

Permit fees: BCA S$200–2,000/flat Source: BCA Builder's Licence framework , SCDF FSC S$1,500–8,000/flat Source: SCDF Fire Safety Certification , URA change-of-use S$535–1,605/flat Source: URA Change of Use guidelines .

What sits inside prelims

Preliminaries (“prelims”) are the non-construction site costs your contractor has to carry. They’re often quoted as a single line at 8–12% of construction, but for a competitive bid you should see them itemised:

  • Site management & supervision. Project manager, foreman, safety officer. Continuous through the build.
  • Hoarding, protection & signage. Mandated by most landlords/MCSTs. CBD A-grade buildings require full-height hoarding with landlord-spec graphics.
  • Insurances. Workmen’s comp, public liability, contractor all-risk. Common landlord requirement.
  • Utilities & consumables. Temporary power, water, waste disposal, daily cleaning.
  • Permits coordination. Submitting plans, attending inspections, closing out. Source: BCA Builder's Licence framework

Scope-change risk — where budgets blow out

Mid-project scope changes are the single biggest reason commercial fit-outs go over budget. A “simple” carpentry upgrade signed off in week 4 often costs 30–40% more than the equivalent decision made in week 0 — because the contractor is mid-flight on adjacent works, and variation orders carry administrative loading.

Three rules to reduce variation cost:

  • Freeze finishes before site-start. Once carpenters mobilise, every change cascades.
  • Itemise variation rates in the contract. Pre-agreed per-line rates avoid surprise markups.
  • Carry contingency in a separate line, not blended into construction. You spend it consciously, not by accident.

Payment milestones

Typical Singapore commercial fit-out payment structure. Avoid contractors who ask for more than 30% upfront — that’s an industry-standard ceiling.

Stage Payment Trigger
Deposit on contract signing20–30%Contract executed, mobilisation
After demolition / strip-out15–20%Existing fit-out removed, site cleared
After partition / M&E rough-in20–25%Frame and services in place
After finishes & carpentry20–25%FOH & finishes complete
On handover5–10%Inspection passed, defects rectified
Retention (12-month DLP)5%Release after defect liability period