How Long Does Commercial Renovation Take in Singapore?

Complete 2026 guide to commercial renovation timelines, project phases, and scheduling strategies for Singapore businesses.

Quick Timeline Reference

Small Office

2-4 weeks

500-1,500 sqft

Retail Store

3-6 weeks

1,000-3,000 sqft

Restaurant

6-12 weeks

Including kitchen

Large Office

8-16 weeks

5,000+ sqft

Complete Project Timeline Breakdown

Phase 1: Planning & Design

Duration: 2-4 weeks

  • • Initial consultation and site survey (1-2 days)
  • • Design development and space planning (1-2 weeks)
  • • Permit application submission (3-5 days)
  • • Final quote and contract signing (3-5 days)

Phase 2: Permits & Approvals

Duration: 2-6 weeks

  • • BCA building plan approval (2-4 weeks)
  • • Fire safety clearance (1-2 weeks)
  • • NEA/PUB approvals if required (2-3 weeks)
  • • Management corporation approval (1 week)

Phase 3: Material Procurement

Duration: 1-3 weeks

  • • Material ordering and delivery scheduling (3-7 days)
  • • Custom fabrication items (1-2 weeks)
  • • Equipment and fixture delivery (5-10 days)
  • • Site preparation and storage setup (2-3 days)

Phase 4: Construction & Fitout

Duration: 2-12 weeks

  • • Demolition and site preparation (3-5 days)
  • • Structural modifications (1-2 weeks)
  • • MEP (Mechanical, Electrical, Plumbing) rough-in (1-2 weeks)
  • • Partitioning and drywall (1-2 weeks)
  • • Flooring and ceiling installation (1-2 weeks)
  • • Painting and finishing work (1-2 weeks)
  • • Final MEP connections and testing (3-5 days)

Phase 5: Completion & Handover

Duration: 1-2 weeks

  • • Final inspections and testing (2-3 days)
  • • Authority approvals and certifications (3-5 days)
  • • Defects rectification (2-5 days)
  • • Handover and documentation (1-2 days)

Factors That Affect Project Duration

Factors That Speed Up Projects

Clear Project Scope

Detailed plans and specifications reduce changes

Standard Finishes

Using readily available materials and fixtures

Experienced Contractors

BCA-registered contractors with proven track records

Minimal Structural Changes

Working within existing layout constraints

Factors That Delay Projects

!

Complex Permit Requirements

Multiple authority approvals for specialized uses

!

Custom Materials

Special orders and fabrication add 2-4 weeks

!

Structural Modifications

Engineering approvals and specialized work

!

Change Orders

Mid-project modifications can add weeks

Detailed Timeline by Business Type

Office Renovation Timeline

Small Office (500-1,500 sqft)

  • • Planning: 1-2 weeks
  • • Permits: 2-3 weeks
  • • Construction: 2-3 weeks
  • Total: 5-8 weeks

Medium Office (1,500-5,000 sqft)

  • • Planning: 2-3 weeks
  • • Permits: 3-4 weeks
  • • Construction: 4-6 weeks
  • Total: 9-13 weeks

Large Office (5,000+ sqft)

  • • Planning: 3-4 weeks
  • • Permits: 4-6 weeks
  • • Construction: 8-12 weeks
  • Total: 15-22 weeks

Retail Store Timeline

Small Retail (500-1,000 sqft)

  • • Planning: 1-2 weeks
  • • Permits: 2-3 weeks
  • • Construction: 2-4 weeks
  • Total: 5-9 weeks

Medium Retail (1,000-3,000 sqft)

  • • Planning: 2-3 weeks
  • • Permits: 3-4 weeks
  • • Construction: 4-6 weeks
  • Total: 9-13 weeks

Large Retail (3,000+ sqft)

  • • Planning: 3-4 weeks
  • • Permits: 4-5 weeks
  • • Construction: 6-10 weeks
  • Total: 13-19 weeks

Restaurant & F&B Timeline

Café/Quick Service

  • • Planning: 2-3 weeks
  • • Permits (including NEA): 4-6 weeks
  • • Construction: 6-8 weeks
  • Total: 12-17 weeks

Full-Service Restaurant

  • • Planning: 3-4 weeks
  • • Permits (multiple authorities): 6-8 weeks
  • • Construction: 10-16 weeks
  • Total: 19-28 weeks

Singapore-Specific Timeline Considerations

Public Holiday Impact

Singapore's public holidays can affect project timelines:

Major Holiday Periods

  • • Chinese New Year: +1-2 weeks delay
  • • Deepavali/Hari Raya: +3-5 days delay
  • • Christmas/New Year: +1 week delay

Permit Processing Delays

  • • Government office closures
  • • Reduced inspection availability
  • • Material delivery delays

Working Hours Restrictions

  • • Residential areas: 9 AM - 6 PM (Mon-Sat)
  • • Commercial buildings: 7 AM - 7 PM (Mon-Sat)
  • • No noisy work on Sundays/holidays
  • • Hacking works: Special hour restrictions

Authority Approval Times

  • • BCA building plans: 2-4 weeks
  • • Fire safety clearance: 1-2 weeks
  • • NEA food establishment: 3-4 weeks
  • • Management corporation: 1-2 weeks

How to Accelerate Your Project Timeline

Pre-Project Preparation

  • 1.
    Finalize scope early: Complete design and specifications before starting permits
  • 2.
    Hire experienced contractors: BCA-registered contractors familiar with local processes
  • 3.
    Submit permits early: Start permit applications before finalizing contractor selection
  • 4.
    Plan material procurement: Order long-lead items during permit phase

During Construction

  • 1.
    Maintain clear communication: Regular project meetings and progress updates
  • 2.
    Avoid scope changes: Minimize modifications during construction phase
  • 3.
    Coordinate inspections: Schedule authority inspections in advance
  • 4.
    Parallel work streams: Overlap tasks where possible (MEP with partitioning)

Get Realistic Timeline Estimates

Connect with experienced BCA contractors for accurate project scheduling

Timeline FAQs

Can I operate my business during renovation?

It depends on the scope. Phased renovations allow partial operation, but full fitouts typically require temporary closure. Discuss phasing options with your contractor to minimize business disruption.

What happens if the project takes longer than estimated?

Good contracts include liquidated damages clauses. However, delays due to permit issues, change orders, or unforeseen conditions may extend timelines. Clear scope definition minimizes overruns.

How accurate are initial timeline estimates?

Experienced contractors can estimate within ±15-20% for well-defined projects. Complex projects with multiple authorities may have greater variance due to approval uncertainties.

Should I plan renovations around peak seasons?

Yes. Avoid Chinese New Year period (Jan-Feb) and year-end holidays for faster completion. Material availability and contractor schedules are better during off-peak periods.