BCA Requirements for Commercial Renovation Singapore

Complete 2026 guide to Building and Construction Authority (BCA) requirements, permits, and compliance for commercial renovation projects in Singapore.

BCA Approval Process

Step 1

Submit Plans

Architectural drawings

Step 2

BCA Review

2-4 weeks processing

Step 3

Approval

Written permit issued

Step 4

Commence

Start construction

When BCA Approval is Required

Approval Required

  • Structural modifications or additions
  • Change of use (e.g., office to restaurant)
  • New or modified fire exits
  • Installing/removing load-bearing walls
  • Mechanical ventilation systems changes
  • Toilet/washroom modifications
  • External facade alterations
  • Mezzanine floor additions

No Approval Needed

  • Interior painting and wallpaper
  • Floor finishes (carpet, tiles, vinyl)
  • Ceiling finishes (non-structural)
  • Lighting fixtures replacement
  • Furniture and built-in cabinets
  • Non-structural partitions
  • Signage (subject to other authorities)
  • Equipment installation (non-structural)

BCA Submission Requirements

Required Documents & Drawings

Architectural Drawings

  • • Site plan (1:500 or 1:1000)
  • • Floor plans (existing & proposed)
  • • Elevation drawings
  • • Cross-sections
  • • Detailed drawings for modifications

Supporting Documents

  • • Form A (Building Plan Application)
  • • Calculation sheets (if applicable)
  • • Fire safety provisions
  • • Accessibility compliance statement
  • • Structural engineer reports

Professional Requirements

Qualified Person (QP)

Licensed architect or engineer to oversee and certify the project.

Builder

BCA-licensed contractor to execute the works.

Specialist Engineers

For MEP systems, structural modifications as required.

Key BCA Regulations for Commercial Renovation

Fire Safety Requirements

Fire Compartmentation

  • • Fire-rated walls and doors
  • • Fire stopping of penetrations
  • • Smoke barriers in large spaces
  • • Fire dampers in ductwork

Means of Escape

  • • Exit width calculations
  • • Emergency lighting
  • • Exit signage compliance
  • • Travel distance limits

Accessibility Requirements

Universal Design

  • • Accessible entrances and routes
  • • Door widths and opening force
  • • Level landings at doorways
  • • Accessible parking provisions

Facilities Provision

  • • Accessible toilet facilities
  • • Counter height requirements
  • • Tactile warning systems
  • • Visual and audible aids

Structural Requirements

Load Bearing Elements

  • • Structural calculations required
  • • Professional engineer certification
  • • Foundation impact assessment
  • • Temporary works approval

Building Envelope

  • • Window and door modifications
  • • Waterproofing requirements
  • • Thermal performance standards
  • • Wind load considerations

MEP Systems Requirements

Electrical Systems

  • • Electrical load calculations
  • • Emergency power provisions
  • • Lightning protection systems
  • • Electrical safety compliance

HVAC & Plumbing

  • • Ventilation requirements
  • • Water supply and drainage
  • • Sanitary fixtures compliance
  • • Energy efficiency standards

BCA Approval Timeline & Process

Typical Approval Timeline

Week 1: Submission

Complete application with all required documents

Week 1-2: Initial Review

BCA preliminary checks and documentation review

Week 2-4: Technical Review

Detailed technical assessment by BCA departments

Week 4-5: Approval/Amendments

Written permit issued or requests for amendments

Factors Affecting Timeline

  • Complexity: Simple projects 2-3 weeks, complex 4-6 weeks
  • Completeness: Complete submissions process faster
  • Amendments: Revisions add 1-2 weeks per cycle
  • Peak periods: Longer processing during busy seasons

Common Delay Reasons

  • Incomplete drawings: Missing details or dimensions
  • Non-compliance: Code violations requiring redesign
  • Missing calculations: Structural or MEP calculations
  • Professional signatures: QP endorsements missing

BCA Approval Fees

Fee Structure

Application Type Base Fee Additional Charges
Minor A&A Works S$200 +S$0.50/sqm floor area
Major A&A Works S$400 +S$1.00/sqm floor area
Change of Use S$300 +S$0.75/sqm floor area
Structural Modifications S$500 +S$1.50/sqm affected area
Amendment Submissions S$100 Per submission

*Fees are subject to change. Check BCA website for latest rates.

Ensuring BCA Compliance

Best Practices for Approval

Early Consultation

Consult BCA or qualified professionals before finalizing designs.

Complete Documentation

Ensure all drawings and documents are complete and accurate.

Code Compliance

Review Building Control Regulations and relevant codes.

Professional Engagement

Work with experienced QPs and BCA-registered contractors.

Common Compliance Issues

Fire Safety Oversights

Inadequate fire compartmentation or exit provisions.

Accessibility Gaps

Missing universal design features or barrier-free access.

Structural Concerns

Unauthorized removal of load-bearing elements.

MEP Non-compliance

Inadequate ventilation or electrical safety provisions.

Need Help with BCA Requirements?

Connect with BCA-registered contractors who understand compliance requirements

BCA Requirements FAQs

Do I need BCA approval for office partition installation?

It depends on the partition type. Non-load bearing partitions that don't affect fire compartmentation typically don't require approval. However, if partitions affect fire exits, ventilation, or are structural, BCA approval is required.

How long does BCA approval take for commercial renovation?

Simple alterations typically take 2-4 weeks for approval. Complex projects involving structural changes or change of use may take 4-6 weeks. Incomplete submissions or non-compliance issues can extend the timeline.

What happens if I renovate without BCA approval?

Unauthorized works may result in stop-work orders, fines, and requirements to demolish non-compliant works. It's always best to check requirements and obtain proper approvals before starting any renovation.

Can I start renovation while waiting for BCA approval?

No, construction cannot commence until written approval is received from BCA. However, you can proceed with non-structural works like painting and furniture installation that don't require approval.

Who can submit BCA applications?

Only Qualified Persons (QPs) - licensed architects or engineers - can submit building plan applications to BCA. Property owners cannot submit applications directly.